To: TID Board Members
Date: August 4, 2004
Re: Directors Report
Project Updates
Liberty Interchange
Work session held with Resource International and BCEO regarding design review of Cox Road extension and Hamilton Mason Road improvements. Next steps include coordination of roadway designs with BCEO Access Management requirements and with landowners adjacent to proposed Cox Road extension.
SR 747 Widening, Phase III
Review of Stage 1 plans on July 9, 2004 at ODOT.
Negotiations complete with BCDES and KZF regarding relocation and improvements to water and sewer line improvements within the project limits. Request Board approval of intergovernmental agreement with Board of County Commissioners regarding the expansion of KZF scope of work and construction of water line improvements as part of the project. All associated costs will be reimbursed to BCTID along with administrative fee.
SR 747 Widening, Phase IV
Closing of Oaks property took place on August 5, 2004. This completes the property acquisition in northwest quadrant of the intersection.
Request Board approval of intergovernmental agreement with Liberty Township authorizing BCTID to make application to the Ohio State Infrastructure Bank for a SIB loan covering the cost of property acquisition. Liberty Township approval of the agreement is anticipated at their meeting on Monday August 16th.
Zone change to B-2 for property in SE quadrant approved by Liberty Township Trustees on August 2nd.
SR 4 Bypass Widening / Butler County Airport Access
Reviewing with Ohio TRAC staff criteria and project score at state level. M-E has provided updated traffic accident information for ODOT consideration and recent identification in Access Ohio of SR4 as a "Priority Corridor" will improve project scoring.
Fairfield Hamilton Corridor Study
No activity
Hamilton North / New Miami River Crossing Study
No activity
7. North SR 4 Bypass Extension
No activity
Other Issues
TIFIA Staff has met with Derek Conklin, Tim Williams, Greg Wilkens, and Brian Coughlin to discuss structure and qualifying projects for a competitive TIFIA loan application.
Port Authority Legal counsel has prepared a draft intergovernmental agreement describing the potential relationship between BCTID and County regarding support for the Port Authority in connection with transportation projects. This draft agreement is currently under review by the parties. Anticipate a request for Board approval of the agreement at the September meeting.
Communication
Upcoming meetings scheduled with the following parties to discuss current projects, potential opportunities and develop relationships for BCTID
- August 11th project meeting for SR 747 Phase IV regarding utility extensions
- August 12th project meeting with Liberty Twp. and BCEO regarding Cox Road and Hamilton Mason Road access management requirements
- August 16th Anticipated Liberty Twp. approval regarding SIB loan application
- August 10th OKI ICC meeting
- August 19th Meeting with Liberty Township and JEDD property owners regarding Liberty Interchange participation
- August 25th TIFIA task force meeting
- September 9th Regional TRAC Public Hearing, Sharonville
- September 13th BCTID Board Meeting