Union Centre

Dedication Ceremony

Project Funding

Construction



Area Map



State Route 129

Union Centre Blvd.

Muhlhauser Road

Union Centre Blvd Extension

State Route 747

Bypass 4/Route 4

Future Projects

 



On August 10, 1997, crews began laying the steel beams for the bridge over I-75. Between the hours of 10 p.m. and 6 a.m., traffic was rerouted over the new exit and entrance ramps. This new method of traffic management during bridge construction was very successful. It allowed maximum efficiency for construction crews. More importantly, it was the safest alternative for I-75 drivers. Expected to take four weeks, this part of the project was finished in only eight nights.